| Program | Pengembangan sarana dan prasarana sekolah |
|---|---|
| Kegiatan | 05.08. Pemeliharaan Sarana dan Prasarana Sekolah |
| Sub Kegiatan | 0 |
| Keterangan | Pemeliharaan Taman |
| No | Nama Barang / Uraian Komponen | Spek Barang | Satuan | Qty | Harga | Jumlah Neto | PPN | PPH | Total |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Tukang Batu (4 Orang X 14 Hari) | Tukang Batu | Orang/Hari | 56 | 183.000 | 10.248.000 | 1.127.280 | 204.960 | 11.375.280 |
| 2 | Semen | 50 Kg | zak | 8 | 76.000 | 608.000 | 66.880 | 12.160 | 674.880 |
| 3 | Pasir | Hitam | Colt | 2 | 330.000 | 660.000 | 72.600 | 13.200 | 732.600 |
| 4 | Cat Tembok | Luar (Weather Sheild) | Kg | 5 | 164.000 | 820.000 | 90.200 | 16.400 | 910.200 |
| 5 | Kuas Cat | 4 Inc | Buah | 5 | 20.600 | 103.000 | 11.330 | 2.060 | 114.330 |
| 6 | Batu Bata | Merah Kelas 1 | Buah | 600 | 1.600 | 960.000 | 105.600 | 19.200 | 1.065.600 |
| 7 | Besi Beton | Dia 10 Mm, 12M | Batang | 15 | 85.000 | 1.275.000 | 140.250 | 25.500 | 1.415.250 |
| 8 | Wastafel | Royal, Panjang | Buah | 1 | 322.000 | 322.000 | 35.420 | 6.440 | 357.420 |
| 9 | Kran Wastafel | nan | Buah | 1 | 189.000 | 189.000 | 20.790 | 3.780 | 209.790 |
| TOTAL | 15.185.000 | 1.670.350 | 303.700 | 16.855.350 | |||||
| Keterangan: 16.855.350 (Sesuai Total) | |||||||||